All Systems Operational

Predictive Maintenance

AI-driven asset health, failure prediction, work order generation

Equipment Health Index
78
/100
Trending stable
Predicted Failures (30d)
3
1 critical · 2 warning
Maintenance Cost Avoidance
$284K
Quarter to date
31%
MTBF
847
hrs
vs 756 last quarter
12%

Asset Health Registry

AssetCategoryHealthStatusRULNext ServiceConf.Action
P-201
Crude Charge Pump
Pump
24
CRITICAL67 hrsOverdue94%
F-101
Crude Filter Skid
Filter
33
WARNING9 daysJun 990%
K-302
Air Compressor
Compressor
41
WARNING14 daysJun 1485%
H-201
Fired Heater
Heater
55
WARNING22 daysJun 2288%
E-104
Crude/Product HX
Heat Exchanger
61
WARNING18 daysJun 887%
E-102
Crude Preheat Train
Heat Exchanger
68
FAIR42 daysJul 1486%
K-301
Overhead Compressor
Compressor
72
FAIR31 daysJul 289%
P-302
Diesel Booster Pump
Pump
76
GOOD62 daysAug 189%
P-104
Naphtha Transfer Pump
Pump
79
GOOD88 daysAug 2890%
V-401
Reflux Drum
Vessel
84
GOOD120 daysSep 2092%
C-101
Atmospheric Column
Column
88
GOOD94 daysAug 1591%
T-301
Diesel Storage Tank
Tank
93
GOOD365 daysMay 202795%

Failure Probability — P-201

Live

Vibration Spectrum — P-201

Anomaly at 2× running speed indicates bearing fault

Work Order Generator

AssetP-201 Crude Charge Pump
Prioritycritical
Est. Duration6 hours
Crew2 mech, 1 elec
Parts Inventory
Mechanical Seal Kit✓ In Stock
Impeller✗ Order Required
Lead time: 4 days

Maintenance Timeline — Next 60 Days

P-201
Pump rebuild — bearings & seals
8d
K-302
Air compressor overhaul
10d
F-101
Filter element replacement
3d
E-104
Heat exchanger cleaning
5d
H-201
Fired heater inspection
7d
K-301
Compressor PM Level 2
4d
E-102
Preheat train cleaning
6d
C-101
Column inspection
8d
Today+15d+30d+45d+60d